2011 MultiFamily
2nd Runner Up
Oakville Mews

Project Statistics
Location: Sidney, B.C., Canada
Type: Townhomes with retail on ground level
Size: 11,000 sq. ft.
ICF Use: 11,800 sq. ft. plus 4,000 sq. ft. interior demising walls
Cost: $4 million
Total Construction: 365 days
ICF Start-to-Finish Time: 105 days

Construction Team
Owner: By the Sea Enterprises
General Contractor: Sorensen Developments
ICF Installer: Black Bamboo Design & Build
Form Distributor: Slegg Construction Materials
Architect: Curtis Miles Architecture
Engineer: JSH Engineering, Ltd
ICF System: LOGIX ICF

Fast Facts

  • ICFs help soundproofing from nearby airport
  • Nine townhomes and five retail spaces
  • Arts & Crafts-style with multiple dormers, decks, and varying floor heights
  • Maintained a popular website and blog documenting construction process
   

 


» MORE MULTIFAMILY 2ND RUNNER UP PHOTOS «