2009 Small Residential
1st Runner Up
The Primrose at Landfall
Project Statistics
Location: Wilmington, NC
Type: Private Residence-Spec Home
Size: 2,777 sq. ft. (floor)
ICF Use: 2,394 sq. ft. (exterior walls)
Cost: $470,000
Project Timeline:
Total Construction: 250 days
ICF Start-to-Finish Time: 8 days
Construction Team
Owner: Mark Johnson Custom Homes
General Contractor: Same as Developer
ICF Installer: Aztec Masonry
Form Distributor: ProBuild East, LLC
Energy Consultant: Above and Beyond Energy
ICF System: Logix ICF
Fast Facts
- Wilmington’s First LEED Platinum Home
- First ICF Home to receive LEED Platinum
HERS Rating of 56
- Saves $2,276 in Energy and 100,000 gal of water annually
- First-time ICF project for Developer/GC
- Gated Community, Limited to choice of four house plans
- Tours for HBA members and Neighborhood residents
- Project featured in four local newspapers and three local television stations
- National coverage in Concrete Homes and Electronic House
|